虚拟电厂参与江苏电网辅助服务市场的探讨
CSTR:
作者:
作者单位:

(1. 国网江苏省电力有限公司,南京 210024;2. 国网江苏省电力有限公司 南京供电分公司,南京 210008;3. 国网江苏省电力有限公司 常州供电分公司,江苏 常州 213003)

作者简介:

杨梓俊(1979),男,江苏靖江人,硕士,高级工程师,研究方向为电网调度运行、综合能源协调控制等;荆江平(1987),男,江苏丹阳人,硕士,高级工程师,研究方向为电网调度运行、综合能源协调控制等;邓星(1984),男,河南许昌人,博士,高级工程师,研究方向为电力系统及其自动化、人工智能、虚拟电厂等。

通讯作者:

中图分类号:

TM734;TM711

基金项目:

国家电网有限公司科技项目“电力弹性负荷快速响应及柔性调节关键技术研究及应用”(SGJSDK00JLJS1800094)


Discussion on virtual power plant participating in ancillary service market of Jiangsu power grid
Author:
Affiliation:

(1. State Grid Jiangsu Electric Power Company, Nanjing 210024, China;2. Nanjing Electric Power SupplyCompany, State Grid Jiangsu Electric Power Company, Nanjing 210008, China;3. State Grid Changzhou PowerSupply Company, State Grid Jiangsu Electric Power Company, Changzhou 213003, China)

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    虚拟电厂可有效聚合负荷侧分布式发电、储能、可调负荷等各类可调资源,从而参与电力辅助服务市场,促进源网荷储能互动运行。首先分析了江苏电力市场用户可调负荷参与辅助服务市场的交易规则,从服务提供者、费用缴纳方与参与方式 3 个方面论述了江苏虚拟电厂参与辅助服务的市场环境,通过分析独立和联营市场模式下的辅助服务市场机制,建立了基于需求响应虚拟电厂的主辅联营模型;接着提出了虚拟电厂参与市场运营的接入规范和实施流程,并以便于高效调度为目标,提出了虚拟电厂-虚拟机组的 2级聚合管理和设计规范。

    Abstract:

    Virtual power plants can effectively aggregate all kinds of adjustable resources, such as load -side distributed power generation, energy storage and adjustable load and so on. Firstly,the trading rules of Jiangsu electric power market in which the users’adjustable load participates in the ancillary service market is analyzed. It also discusses the market environment of Jiangsu virtual power plant participation in auxiliary services from three aspects: service provider, fee payer and participation mode, and establishes the main auxiliary joint venture model based on demand response virtual power plant by analyzing the auxiliary service market mechanism under the independent and joint market model. Secondly, the access specification and implementation process for virtual power plant to participate in market operation are put forward,and for the purpose of efficient scheduling, the 2 -level aggregate management and design specification of virtual power plant and virtual unit is proposed.

    参考文献
    相似文献
    引证文献
引用本文

杨梓俊,荆江平,邓 星,叶 婷,陈 辉,高 阳.虚拟电厂参与江苏电网辅助服务市场的探讨[J].电力需求侧管理,2021,23(4):90-95

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2021-03-05
  • 最后修改日期:2021-05-31
  • 录用日期:
  • 在线发布日期: 2021-08-04
  • 出版日期:
文章二维码